CorporateMuscatDelivered November 20, 2025

The contractor was losing hours to heat inside a steel container. We supplied a 24 m² insulated timber office with a meeting corner, split AC, and cabling raceways. Measured interior temperature dropped by 11°C at midday, and the unit is relocatable to the next site.